Battersea Power Station Phase 3A

Contractor: Sir Robert McAlpine

Client: Permasteelisa (UK) Ltd.

Start Date: 2 September 2020

Finish Date: 2 September 2022

 

Façade Installations BUILDING 1/ PP1: 

- Unitized System 7,256 m2

- Fascia Spandrel, Cladding, Soffits, Cills 6,479 m2

- Smoke & fire barriers at slab edge connection 2,656 m1

- Flyservice brackets 906 no
- Sliding Doors, Double Doors and Single Doors

 

 

Façade Installations BUILDING 2/ PP2: 

- Unitized System 9,075 m2

- Fascia Spandrel, Cladding, Soffits, Cills 6,605 m2

- Smoke & fire barriers at slab edge connection 3,444 m1

- Flyservice brackets 1,336 no

- Sliding Doors, Double Doors and Single Doors 

 

 

Façade Installations PODIUM: 

Opaque and glazed steel Stick System elements 2,937 m2

- Canopy steel structures, glazing and pipeworks

- Cladding

- Stainless Steel Gutter
- Rainwater Pipes