Plot 205 Greenwich Peninsula
![](/images/share_fb.png)
Main Contractor: MACE
Client: Permasteelisa (UK) Limited
Start Date: 26 September 2016
Finish Date: 30 November 2018
Façade Installations BUILDING 1:
- Curtain Wall Stick System 1,527 m2
- Unitized System 10,910 m2
- Unitized rain screen cladding 3,270 m2
- Balcony screen 2,343 m2
- Balustrades 2,136 m2
- Balconies sliding doors 970 m2
- Copings 600 m1
Façade Installations BUILDING 2:
- Curtain Wall Stick System 879 m2
- Unitized System 9,494 m2
- Unitized rain screen cladding 2,633 m2
- Balcony screen 1,616 m2
- Balustrades 2,136 m2
- Balconies sliding doors 668 m2
- Copings 560 m1